Municipal Finance and Capacity Building (MFCB) Programme
Programme Status
Last Update: December 5, 2022 |
Time Elapsed: 97% |
Start Date: 1 Feb 2019 |
Expected Completion Date: 31 January 2023 |
Total Activities: 49 |
Completed Activities: 14 |
Output level Progress status
A. Physical Progress
Progress Status |
Previous Progress % |
Current Progress % |
Completed Activities |
Output1: Enhanced capacity of municipalities to develop/ update long term strategic plan |
37 |
39 |
1. Inception Workshop (1.1.1) 2. Prepare Revenue Improvement Action Plan (RIAP)- 1.1.7 3. Procurement and Contract Management Training (1.1.8) 4. Conduct seminars/workshops for advocating climate resilient and sustainable urban infrastructures (1.1.12) |
Output2: Enhanced Capacity of municipalities to develop investment pipeline for improved urban infrastructure and services |
29 |
29 |
1. Conduct pre-feasibility study for potential investments (2.1.2)
|
Output3: Enhanced Capacity of municipalities to develop investment pipeline for improved urban infrastructure and services |
65 |
65 |
1. Training on Participatory planning and budgeting process (3.1.1) 2. Support municipalities to prepare communication strategy for citizen engagement and public accountability in municipal services and taxation (3.2.1) 3. Prepare common Grievance handling policy and operation manual for municipality (3.2.4) |
Output4: Enhanced Capacity of municipalities to develop investment pipeline for improved urban infrastructure and services |
35 |
42 |
1. Conduct Study on gap analysis between best practices of other relevant municipal development banks and TDF (4.1.2) 2. Support for preparation of Municipal Investment Facility guidelines including revision of existing common loan and grants policy (4.2.1) 3. Develop loan recovery policy and guidelines for TDF (4.2.2) 4. Develop Potential Impact Investment Concept Notes (related to climate resilient urban infrastructure) for implementation (4.2.4) 5. Develop PPP financing policy, manual/guidelines for TDF (4.3.2) |
Average Physical progress, % as of November 2022 |
42 |
44 |
|
MFCB Activities Progress Status
Ref No. |
Activities |
Expected Completion Date |
Oct Progress, % |
Nov Progress, % |
Status |
Plan |
1.1.1 |
Inception workshop |
April-19 |
|
100 |
Complete |
|
1.1.2 |
Support for preparation and review of municipal Strategic Plan and Profiling |
Dec-22 |
47 |
60 |
9-IUDPs with projects and 9-DEDs reviewed; extracted and recommended 7 bankable projects |
Review and report findings- 10 IUDPs |
1.1.3 |
Support for preparation of common LED Strategy for municipalities |
Dec-22 |
5 |
5 |
Document complete for procurement-ToR complete |
Once LED document from MOFAGA; will be materialized |
1.1.4 |
Municipal Financing Strategy Developed |
Nov-22 |
5 |
5 |
Evaluation complete |
Contract agreement |
1.1.5 |
Training and Preparation of Medium Term Expenditure Plan for the Municipality |
Aug-22 |
15 |
55 |
MTEP draft plan submitted |
Contract administration |
1.1.6 |
Training and Preparation of Capital Investment Plan and Asset Management Plan |
Aug-22 |
15 |
15 |
RFP evaluation complete |
Contract agreement |
1.1.7 |
Prepare Revenue Improvement Action Plan (RIAP) |
Aug-22 |
70 |
70 |
Complete |
|
1.1.8 |
Procurement and Contract Management Training |
|
100 |
100 |
Complete |
|
1.1.9 |
Support Preparation of Procurement Plans |
Aug-22 |
0 |
0 |
|
Plan and expedite |
1.1.10 |
Prepare ICT based Guidelines and procedure document for IPT/Business Tax and House Rent Tax |
Aug-22 |
15 |
30 |
Field Report Received |
|
1.1.12 |
Conduct seminars/workshops for advocating climate resilient and sustainable urban infrastructures |
Sep-22 |
20 |
20 |
Complete |
|
1.1.13 |
Organize workshops to prepare civic education materials on disaster risk reduction for CBOs |
Sep-22 |
20 |
20 |
Event preparation completed |
Proceed training event |
1.2.1 |
Support Selected pilot municipalities in automation of financial reporting including expenditure tracking system |
Aug-22 |
5 |
5 |
Device specification prepred for procuremet of goods (device) |
Procure devices and support to municipalities compatible to software |
1.2.2 |
Support pilot municipalities in designing and implementing street addressing system and house numbering system |
Nov-22 |
35 |
55 |
Draft report received |
|
1.2.3 |
Support to establish database of key taxes and service delivery in selected pilot municipalities |
Nov-22 |
15 |
15 |
RFP Evaluation process |
Procure firms |
1.2.4 |
Introduce e-building permit system |
Dec-22 |
15 |
15 |
EoI Evaluation process |
Issue RFP |
1.2.5 |
Support ICT-based municipal service delivery |
Dec-22 |
15 |
15 |
RFP Evaluation process |
Issue RFP |
1.2.6 |
Conduct advanced ICT Training to key officials of selected pilot municipalities for implementation of integration of revenue and service delivery |
Nov-22 |
5 |
5 |
Concept Note prepared: Training is related to 1.2.3 & 1.2.5 |
First complete 1.2.3 and 1.2.5 then conduct training |
2.1.1 |
Training and support on project development, including checklist, screening and prioritization of potential projects |
Nov-22 |
15 |
15 |
Concept note prepared |
Finalize the Guideline |
2.1. 2 |
Conduct pre-feasibility study for potential investments |
Feb-22 |
100 |
100 |
16 projects have been selected for DPR study |
|
2.1.3 |
Prepare Detailed Project Reports for bankable investment projects |
Dec-22 |
15 |
15 |
RFP Evaluation process |
|
2.1.4 |
Support Design and Finance for urban regeneration including land development |
Dec-22 |
15 |
15 |
RFP Evaluation process |
|
2.1.5 |
Develop feasibility/DPR project pipeline for Smart Water Grid (SWG) |
Aug-22 |
0 |
0 |
Preliminary discussion held, waiting for concept note |
Coordinate with the team-Municipality, water supply board |
3.1.1 |
Training on Participatory planning and budgeting process |
Sep-22 |
20 |
100 |
Concept note prepared |
|
3.2.1 |
Support municipalities to prepare communication strategy for citizen engagement and public accountability in municipal services and taxation |
Aug-22 |
55 |
100 |
Complete |
|
3.2.2 |
Support mechanisms to disclose key information in the municipality website in accordance with Right to Information Act |
Jan-23 |
10 |
10 |
Training module completed |
Conduct web based information sharing |
3.2.3 |
Support to ensure public hearing are conducted |
Jan-23 |
80 |
80 |
Public hearing-Notes collected from concerned municipalities (f.y. 2078/79); Checklist developed for fy 2079/80 |
|
3.2.4 |
Prepare common Grievance handling policy and operation manual for municipality |
Nov-22 |
55 |
100 |
Complete |
|
3.2.5 |
Support CSO capacity for demand of services |
Sep-22 |
0 |
0 |
– |
Prepare concept note |
4.1.1 |
Conduct Credit Rating Assessment of TDF |
Oct-22 |
20 |
20 |
ToR Finalized |
Procure consultant |
4.1.2 |
Conduct Study on gap analysis between best practices of other relevant municipal development banks and TDF |
Sept-22 |
100 |
100 |
Final report received |
|
4.1.3 |
Strengthen TDF’s online municipal project finance application system |
Dec-22 |
10 |
10 |
Concept Note finalized; requirement analysis complete |
Prepare consulting report |
4.1.4 |
Strengthen database and M/E system of TDF |
Dec-22 |
70 |
85 |
System developed; final testing process |
Follow up |
4.1.5 |
Strengthen TDF’s Appraisal System |
Aug-22 |
20 |
55 |
Draft report reveived |
Follow up |
4.1.6 |
Preparation of DPR of model green building |
Dec-22 |
20 |
25 |
Preliminary demo presented |
|
4.1.7 |
Provincial workshop conducted in 7 provinces on TDF’s Business Products, Services and application procedures tec. |
Dec-22 |
71 |
71 |
Supplementary workhop planned to conduct in December |
|
4.1.8 |
Support the preparatory works for bond issuance strategy and guidelines |
Dec-22 |
0 |
0 |
Sr. Banker will work out while on board |
|
4.1.9 |
Conduct Market Study for bond issuance |
Oct-22 |
0 |
0 |
Sr. Banker will work out while on board |
|
4.2.1 |
Support for preparation of Municipal Investment Facility guidelines including revision of existing common loan and grants policy (Infrastructure Financing Guideline 01) |
Jan-22 |
100 |
100 |
Complete |
|
4.2.2 |
Develop loan recovery policy and guidelines for TDF |
Oct-21 |
100 |
100 |
Complete |
|
4.2.3 |
Develop Impact Investment Strategy and Operation systems |
Nov-22 |
0 |
0 |
Not started |
Draft ToR |
4.2.4 |
Develop Potential Impact Investment Concept Notes (related to climate resilient urban infrastructure) for implementation |
Nov-22 |
30 |
100 |
Complete |
|
4.2.5 |
Develop feasibility studies and DPRs for climate resilient urban infrastructure |
Dec-22 |
15 |
15 |
ToR for detailed study drafted |
Proceed for RFP with revisiting ToR |
4.2.6 |
Support advocacy and policy intervention on various related thematic areas including energy efficiency investments |
Dec-22 |
0 |
0 |
Not started |
|
4.2.7 |
Conduct workshops and conferences on lessons learned from the MFCB pertaining to municipal finance |
Jan-23 |
0 |
0 |
Draft concept note, and discussion models |
|
4.3.1 |
Conduct workshop and initiation of PPP for high impact projects |
Oct-22 |
0 |
0 |
Concept note under preparation |
Develop concept note and workout while PPP Expert on board |
4.3. 2 |
Develop PPP financing policy, manual/guidelines for TDF |
May-22 |
100 |
100 |
Complete |
|
4.4 |
Conduct Impact Assessment of sector wise projects supported by TDF (Water Supply, Bus Park and Commercial Complex) including TDF’s contribution to the national economy |
Jul-22 |
25 |
25 |
Inception report received |
Follow up |
4.5 |
Conduct Study on TDF’s role, opportunities and challenges in the changed federal context |
Dec-22 |
0 |
0 |
Draft ToR |
|
4.6 |
Conduct Twinning Programme with an International Agency working on municipal infrastructure financing institution, such as Netherlands Municipal Bank (BNG) and Exposure Visits 18 personnel for Capacity Development |
0 |
0 |
|
B. Financial Progress
MFCB Program Expenditure Status (Contract No: CSO-LA/208/402-797)
Reporting period: July-October, 2022
SN |
Expenditure |
Budget (EUR) |
Cumulated Expenses till 31 Jan 2022 |
Expenditure incurred from 1 Feb 2022 to 30 Oct 2022 |
Cumulated Expenditure till 30 Oct 2022 |
1 |
Human Resources |
211,219.52 |
26,715.75 |
28,802.34 |
55,518.09 |
2 |
Travel |
50,908.25 |
2,123.65 |
5,944.32 |
8,067.97 |
3 |
Equipment and supplies |
404,632.00 |
82,657.10 |
– |
82,657.10 |
4 |
Local office |
48,371.00 |
13,795.87 |
14,428.44 |
28,224.32 |
5 |
Other costs, services |
719,566.00 |
54,080.57 |
35,377.92 |
89,458.49 |
6 |
Other |
600,548.00 |
88,372.34 |
115,222.28 |
203,594.62 |
7 |
Subtotal of (1-6) |
2,035,245 |
267,745.28 |
199,775.30 |
467,520.58 |
8 |
Indirect cost (2% of 7) |
40,704.90 |
5,354.91 |
3,995.51 |
9,350.41 |
9 |
Total eligible costs of the Action, excluding reserve and volunteers’ work (7+ 8) |
2,075,949.67 |
273,100.19 |
203,770.81 |
476,871.00 |
10 |
10.1 Provision for contingency reserve (maximum 2% of 7, subtotal of direct eligible costs of the Action) |
40704.8954 |
5,354.91 |
3,995.51 |
9,350.41 |
11 |
Total eligible costs (9+10) |
2,116,654.56 |
278,455.09 |
207,766.32 |
486,221.41 |
12 |
Taxes |
– |
– |
– |
– |
13 |
Total accepted costs of the Action (11+12) |
2,116,654.56 |
278,455.09 |
207,766.32 |
486,221.41 |
|
Received- Installment 1 |
280,534.00 |
|
|
|
Received- Installment 2 |
1,382,477.00 |
||||
Total received |
1,663,011.00 |
29.24% |
|||
Total programme budget (EUR) |
1,996,191.00 |
|
Fin-Progress |
24.36% |
C. Next Month Plan
Major task and process oriented activities have been planned for the next month:
Output1 |
· (1.1.2) Review of 4 Strategic Plans and extract bankable projects for TDF; collect IUDPs at least 8 from DUDBC · (1.1.13) Organize workshops to prepare civic education materials on disaster risk reduction for CBOs |
Output2 |
· Complete procurement process of task oriented activities · Follow up consultants for timely completion of tasks and ensure output quality |
Output3 |
· Complete procurement process of task oriented activities · Follow up consultants for timely completion of tasks and ensure output quality |
Output4 |
· Complete procurement process of task oriented activities · Follow up consultants for timely completion of tasks and ensure output quality |
Others |
· Finalize a programme implementation sharing workshop on status of MFB for newly elected municipal representatives · Follow up of ongoing contract packages of task oriented activities |
D. Issues and Challenges
- Series of festivals Provincial and Federal level election had short term delay in programme implementation.
- The contract management for task oriented activities are to significantly improved with duly follow up of contract administration
- To proceed time taking consulting tasks, for example, preparation of DPRs for bankable projects is still uncertain due to the programme implementation short period and undecided due to waiting of zero budget programme extension.
- Some major process oriented activities are substantially pending due to the absence of Experts, who were supposed to be hired.