Municipal Finance and Capacity Building (MFCB) Programme
Programme Status
Last Update: October 9, 2022 |
|
Start Date: 1 Feb 2019 |
|
Expected Completion Date: 31 January 2023 |
|
Total Activities: 49 |
|
Completed Activities: 12 |
|
Time Elapsed: 93% |
|
Output level Progress status
Physical Progress
Progress Status |
Previous Progress % |
Current Progress % |
Completed Activities |
Output1: Enhanced capacity of municipalities to develop/ update long term strategic plan |
32 |
39 |
1.Inception Workshop (1.1.1) 2.Prepare Revenue Improvement Action Plan (RIAP)- 1.1.7 3.Procurement and Contract Management Training (1.1.8) 4.Conduct seminars/workshops for advocating climate resilient and sustainable urban infrastructures (1.1.12) |
Output2: Enhanced Capacity of municipalities to develop investment pipeline for improved urban infrastructure and services |
29 |
29 |
1.Conduct pre-feasibility study for potential investments (2.1.2)
|
Output3: Enhanced Capacity of municipalities to develop investment pipeline for improved urban infrastructure and services |
52 |
65 |
1.Training on Participatory planning and budgeting process (3.1.1) 2.Support municipalities to prepare communication strategy for citizen engagement and public accountability in municipal services and taxation (3.2.1) 3.Prepare common Grievance handling policy and operation manual for municipality (3.2.4) |
Output4: Enhanced Capacity of municipalities to develop investment pipeline for improved urban infrastructure and services |
33 |
35 |
1.Conduct Study on gap analysis between best practices of other relevant municipal development banks and TDF (4.1.2) 2.Support for preparation of Municipal Investment Facility guidelines including revision of existing common loan and grants policy (4.2.1) 3.Develop loan recovery policy and guidelines for TDF (4.2.2) 4.Develop PPP financing policy, manual/guidelines for TDF (4.3.2) |
Average Physical progress, % as of September 2022 |
36 |
42 |
|
MFCB Activities Progress Status
Ref No. |
Activities |
Expected Completion Date |
Previous Progress, % |
Current Progress, % |
Status |
Plan |
1.1.1 |
Inception workshop |
April-19 |
|
100 |
Complete |
|
1.1.2 |
Support for preparation and review of municipal Strategic Plan and Profiling |
Dec-22 |
47 |
60 |
5-IUDPs and 9 DEDs reviewed; extracted and recommended 7 bankable projects |
Review and report findings- 10 IUDPs |
1.1.3 |
Support for preparation of common LED Strategy for municipalities |
Dec-22 |
5 |
5 |
Document complete for procurement-ToR complete |
Once LED document from MOFAGA; will be materialized |
1.1.4 |
Municipal Financing Strategy Developed |
Nov-22 |
5 |
5 |
ToR finalized |
Contract agreement |
1.1.5 |
Training and Preparation of Medium Term Expenditure Plan for the Municipality |
Aug-22 |
15 |
20 |
MTEP under preparation |
Contract administration |
1.1.6 |
Training and Preparation of Capital Investment Plan and Asset Management Plan |
Aug-22 |
15 |
15 |
RFP Evaluation |
Contract agreement |
1.1.7 |
Prepare Revenue Improvement Action Plan (RIAP) |
Aug-22 |
70 |
70 |
Complete |
|
1.1.8 |
Procurement and Contract Management Training |
|
100 |
100 |
Complete |
|
1.1.9 |
Support Preparation of Procurement Plans |
Aug-22 |
0 |
0 |
– |
Plan and expedite |
1.1.10 |
Prepare ICT based Guidelines and procedure document for IPT/Business Tax and House Rent Tax |
Aug-22 |
15 |
25 |
Inception Report Received |
|
1.1.12 |
Conduct seminars/workshops for advocating climate resilient and sustainable urban infrastructures |
Sep-22 |
20 |
20 |
Complete |
|
1.1.13 |
Organize workshops to prepare civic education materials on disaster risk reduction for CBOs |
Sep-22 |
20 |
20 |
Event preparation completed |
Proceed training event |
1.2.1 |
Support Selected pilot municipalities in automation of financial reporting including expenditure tracking system |
Aug-22 |
5 |
5 |
Device specification prepared for procurement of goods (device) |
Procure devices and support to municipalities compatible to software |
1.2.2 |
Support pilot municipalities in designing and implementing street addressing system and house numbering system |
Nov-22 |
35 |
55 |
Draft report received |
|
1.2.3 |
Support to establish database of key taxes and service delivery in selected pilot municipalities |
Nov-22 |
15 |
15 |
RFP Evaluation |
Procure firms |
1.2.4 |
Introduce e-building permit system |
Dec-22 |
15 |
15 |
Eoi Evaluation |
Issue RFP |
1.2.5 |
Support ICT-based municipal service delivery |
Dec-22 |
15 |
15 |
RFP Evaluation |
Issue RFP |
1.2.6 |
Conduct advanced ICT Training to key officials of selected pilot municipalities for implementation of integration of revenue and service delivery |
Nov-22 |
5 |
5 |
Training is related to 1.2.3 & 1.2.5 |
First complete 1.2.3 and 1.2.5 then conduct training |
2.1.1 |
Training and support on project development, including checklist, screening and prioritization of potential projects |
Nov-22 |
15 |
15 |
Concept note prepared |
Finalize the Guideline |
2.1. 2 |
Conduct pre-feasibility study for potential investments |
Feb-22 |
100 |
100 |
Complete-16 projects selected for DPR study |
|
2.1.3 |
Prepare Detailed Project Reports for bankable investment projects |
Dec-22 |
15 |
15 |
RFP Evaluation |
|
2.1.4 |
Support Design and Finance for urban regeneration including land development |
Dec-22 |
15 |
15 |
RFP Evaluation |
|
2.1.5 |
Develop feasibility/DPR project pipeline for Smart Water Grid (SWG) |
Aug-22 |
0 |
0 |
Preliminary discussion held, waiting for concept note |
Coordinate with the team-Municipality, water supply board |
3.1.1 |
Training on Participatory planning and budgeting process |
Sep-22 |
20 |
100 |
Complete |
|
3.2.1 |
Support municipalities to prepare communication strategy for citizen engagement and public accountability in municipal services and taxation |
Aug-22 |
55 |
100 |
Complete |
|
3.2.2 |
Support mechanisms to disclose key information in the municipality website in accordance with Right to Information Act |
Jan-23 |
10 |
10 |
Training module developed |
Conduct web based information sharing |
3.2.3 |
Support to ensure public hearing are conducted |
Jan-23 |
80 |
80 |
Public hearing-Notes collected from concerned municipalities (f.y. 2078/79); Checklist developed for fy 2079/80 |
|
3.2.4 |
Prepare common Grievance handling policy and operation manual for municipality |
Nov-22 |
55 |
100 |
Complete |
|
3.2.5 |
Support CSO capacity for demand of services |
Sep-22 |
0 |
0 |
– |
Prepare concept note |
4.1.1 |
Conduct Credit Rating Assessment of TDF |
Oct-22 |
20 |
20 |
ToR finalized |
Procure consultant |
4.1.2 |
Conduct Study on gap analysis between best practices of other relevant municipal development banks and TDF |
Sept-22 |
100 |
100 |
Complete |
|
4.1.3 |
Strengthen TDF’s online municipal project finance application system |
Dec-22 |
10 |
10 |
Concept Note finalized |
Prepare consulting report |
4.1.4 |
Strengthen database and M/E system of TDF |
Dec-22 |
70 |
85 |
System developed; final testing process |
Follow up |
4.1.5 |
Strengthen TDF’s Appraisal System |
Aug-22 |
20 |
20 |
Inception report received |
Follow up |
4.1.6 |
Preparation of DPR of model green building |
Dec-22 |
20 |
20 |
Consultant mobilized |
|
4.1.7 |
Provincial workshop conducted in 7 provinces on TDF’s Business Products, Services and application procedures tec. |
Dec-22 |
71 |
71 |
Supplementary workshop planned to conduct as favorable time |
|
4.1.8 |
Support the preparatory works for bond issuance strategy and guidelines |
Dec-22 |
0 |
0 |
– |
Sr. Banker will work out while on board |
4.1.9 |
Conduct Market Study for bond issuance |
Oct-22 |
0 |
0 |
– |
Sr. Banker will work out while on board |
4.2.1 |
Support for preparation of Municipal Investment Facility guidelines including revision of existing common loan and grants policy (Infrastructure Financing Guideline 01) |
Jan-22 |
100 |
100 |
Complete |
|
4.2.2 |
Develop loan recovery policy and guidelines for TDF |
Oct-21 |
100 |
100 |
Complete |
|
4.2.3 |
Develop Impact Investment Strategy and Operation systems |
Nov-22 |
0 |
0 |
– |
Draft ToR |
4.2.4 |
Develop Potential Impact Investment Concept Notes (related to climate resilient urban infrastructure) for implementation |
Nov-22 |
30 |
70 |
Developed 7 Concept notes (Potential Impact Investment- related to climate resilient urban infrastructure) |
3 Concept notes to be developed |
4.2.5 |
Develop feasibility studies and DPRs for climate resilient urban infrastructure |
Dec-22 |
15 |
15 |
ToR for detailed study drafted |
Proceed for RFP with revisiting ToR |
4.2.6 |
Support advocacy and policy intervention on various related thematic areas including energy efficiency investments |
Dec-22 |
0 |
0 |
– |
|
4.2.7 |
Conduct workshops and conferences on lessons learned from the MFCB pertaining to municipal finance |
Jan-23 |
0 |
0 |
– |
Draft concept note, and discussion models |
4.3.1 |
Conduct workshop and initiation of PPP for high impact projects |
Oct-22 |
0 |
0 |
Concept note under preparation |
Develop concept note and workout while PPP Expert on board |
4.3. 2 |
Develop PPP financing policy, manual/guidelines for TDF |
May-22 |
100 |
100 |
Complete |
|
4.4 |
Conduct Impact Assessment of sector wise projects supported by TDF (Water Supply, Bus Park and Commercial Complex) including TDF’s contribution to the national economy |
Jul-22 |
25 |
25 |
Inception report received |
Follow up |
4.5 |
Conduct Study on TDF’s role, opportunities and challenges in the changed federal context |
Dec-22 |
0 |
0 |
– |
Draft ToR |
4.6 |
Conduct Twinning Programme with an International Agency working on municipal infrastructure financing institution, such as Netherlands Municipal Bank (BNG) and Exposure Visits 18 personnel for Capacity Development |
0 |
0 |
– |
|